FBI Probing Trumbull Sewer Project

FBI investigators are reportedly scrutinizing the negotiations between the Town and Bridgeport-based Mark IV Construction, the original low bidder for the project.

Federal authorities are reportedly investigating alleged improprieties in the for the that's in .

According to a report in the CT Post, FBI investigators are scrutinizing the bidding and contract negotiations between the Town and Bridgeport-based Mark IV Construction, the original low bidder for the project.

Mark IV reportedly submitted a significantly lower estimate when the project was put out to bid in 2007, however the company ended up requesting numerous change orders during the construction process, which the Town approved, resulting in the final price tag jumping to about $20.7 million — almost as much as the original high bidder.

Find out what's happening in Trumbullwith free, real-time updates from Patch.

Meanwhile the for $18 million to recover operational costs, remediation and repair of defect costs; as well as to recoup $464,000 in overpayments and consultant and attorneys' costs, the report states. What's more, Mark IV owner Manuel Moutinho has reportedly filed a countersuit against the Town for defamation.

Adding another element is the , who became the subject of some controversy in town for serving as a consultant on the project while also serving on the town .

Find out what's happening in Trumbullwith free, real-time updates from Patch.

For more, check out the CT Post report.

We’ve removed the ability to reply as we work to make improvements. Learn more here